Wiegand-Glas’ plant in Schleusingen, Germany has recently installed two Zippe pre-silos brought in and lifted for its tank 2.
The two Zippe silos were brought in via the cold-end hall and then lifted into place immediately afterwards. This was able to happen due to the tank building being already closed.
The silos were be assembled in just one day thanks to experienced Zippe supervisor Karl Möller, along with other members of the Zippe team and Wiegand-Glas staff on site.
The new tank, which will be supplied with batch from these two silos, is scheduled to start production next year.
09.12.2020, Wiegand-Glas
Материал новостей на Сайте - авторское право и принадлежит Компании или третьему лицу, поставщику новостей , и все права сохранены. Любой Пользователь, который получает доступ к такому материалу, может делать это только в целях собственного использования, и использование такого материала - риск для самого Пользователя. Перераспределение или другая коммерческая эксплуатация такого материала новостей явно запрещены. Где такой материал новостей обеспечен третьим лицом, каждый Пользователь соглашается наблюдать и быть связанным определенными условиями использования, относящимися к такому материалу новостей. Мы не представляем или подтверждаем точность, или надежность любой информации содержащейся в любых новостях или внешних веб-сайтах, упомянутых в новостях.
Если содержание или оформление этих станиц нарушает права третьих лиц или положения закона, тогда мы просим о соответствующем уведомлении без необходимых издержек. Я ручаюсь, что по праву вызванное недовольство место в тексте будет незамедлительно удалено, не требуя подключения поверенного лица с Вашей стороны. Однако вызванные Вами расходы без преждевременного установления конакта будут нами в полной мере отклонены и при необходимости мы подадим встречную жалобу касательно нарушения вышеназванных положений.